Space Station Status Report for May 20
What's happening on the Space Station.
ISS Status Reports Download time: May 21 2011 9:09 AM ET
All ISS systems continue to function nominally, except those noted previously or below. FE-3 Ron Garan continues on his special Shuttle-crew sleep-cycle schedule: Wake – 10:26pm last night; Sleep – 12:56pm-9:26pm today.
Mission ULF-6's EVA-1 was completed successfully by EV1 Greg Chamitoff & EV2 Drew Feustel in 6h 19m, accomplishing all objectives. Beginning this morning at 3:10am EDT, the spacewalk ended at 9:29am. [EV1 & EV2 began their "campout" yesterday around noon in the U.S. Airlock (A/L) at ~12:51pm with hatch closure and depressurization of the Crewlock (CL) from 14.7 to 10.2 psi, followed by mask prebreathe (~12:51pm-1:36pm) and sleep from 2:26pm-10:26pm. After wake-up at nighttime and the usual hygiene break/with mask prebreathe for Taz & Drew at 11:01pm-12:11am, the A/L hatch was closed again by Ron Garan & Mark Kelly for EVA preps in 10.2 psi (12:11am-1:41am), followed by EMU purge (1:41am-1:56am) and prebreathe in the EMUs (1:56am-2:46am). Afterwards, with CL depressurization and EV1/EV2 switching to suit power, EVA-1 began at 3:10am. The excursion lasted 6h 19m.]
During EVA-1, Greg & Drew –
• Retrieved the MISSE-7A & 7B experiments from ELC-2 (Express Logistics Carrier 2),
• Installed the MISSE-8 experiment
• Installed segment S3 CETA (Crew Equipment Translation Aid) light,
• Installed a cover (#7) on the Stbd SARJ,
• Installed NH3 (ammonia) refill jumpers between segments P3-P4, P5-P6, P6-EAS (Early Ammonia Server) on the left-side truss;
• Stowed the P4 NH3 jumper,
• Connected P3-P4, P1-P2 & P16A/J16A,
• Vented nitrogen from NH3 server;
• Reconfigured the QD (quick disconnect) tool bag,
• Installed EWC (External Wireless Communication) antenna on US Lab for comm to the truss-mounted ELCs, and
• Cleaned up.…